Configuration Schedule for Cycle 5
Complete Cycle 5 Configuration Schedule
Start date | End date | Config | min - max baseline (m) | beam (")1 | maximum recoverable scale (")1 |
---|---|---|---|---|---|
2017-10-01 | 2017-10-22 | C43-10 | 244-16200 | 0.042" | 0.50" |
2017-10-22 | 2017-11-07 | C43-9 | 368-13900 | 0.057" | 0.81" |
2017-11-07 | 2017-11-27 | C43-8 | 110-8500 | 0.096" | 1.4" |
2017-11-27 | 2017-12-07 | C43-7 | 64-3600 | 0.21" | 2.6" |
2017-12-07 | 2018-01-10 | C43-6 | 15-2500 | 0.31" | 4.1" |
2018-01-10 | 2018-02-01 | C43-5 | 15-1400 | 0.54" | 6.7" |
2018-02-01 | 2018-02-28 | February Maintenance Period | |||
2018-03-01 | 2018-03-30 | C43-4 | 15-784 | 0.92" | 11.2" |
2018-03-30 | 2018-05-05 | C43-3 | 15-500 | 1.4" | 16.2" |
2018-05-05 | 2018-06-05 | C43-2 | 15-314 | 2.3" | 22.6" |
2018-06-05 | 2018-07-22 | C43-1 | 15-161 | 3.4" | 29.0" |
2018-07-22 | 2018-08-15 | C43-2 | 15-314 | 2.3" | 22.6" |
2018-08-15 | 2018-08-30 | C43-3 | 15-500 | 1.4" | 16.2" |
2018-08-30 | 2018-09-15 | C43-4 | 15-784 | 0.92" | 11.2" |
2018-09-15 | 2018-09-30 | C43-5 | 15-1400 | 0.54" | 6.7" |
1The synthesized beam and maximum recoverable scale are tabulated for a frequency of 100 GHz. To calculate these quantities for a given frequency (measured in GHz), multiply the tabulated values by (100 / frequency).
NOTE: The Configuration Schedule is SUBJECT TO CHANGE.